From: Phil Hunter, Hannah Avenue Project Supervisor....
To All:
See the [above] attached information update.
The tentative schedule is to remove the south half of the Hanna and Shelby intersection for asphalt replacement beginning at 6:00 p.m. on Friday, June 10, 2011.
This area will be closed until approximately 11:59 p.m. on Sunday, June 12.
Please contact me if you have any questions.
Phillip Hunter
Project Supervisor
Bernardin, Lochmueller and Associates, Inc.